The Task
Our customer has constructed a MATIERE Pre-cast Arch System to form a cut and cover tunnel, allowing passage of a commercial rail line with the construction of a dual carriageway above. The outer surface of the interlocking pre-cast tunnel sections required a waterproof geomembrane barrier for which F.L.I. Environmental was awarded the contact.

The Solution
F.L.I. Environmental proposed the use of 2mm thick HDPE (High Density Polyethylene) lining, which was placed in panels across the circumference of the tunnel. At the leading edge of each open end of the tunnel liner was continuously fixed to the structure using a stainless steel batten, bolted into the concrete. A neoprene gasket strip was used beneath the liner to ensure a watertight joint. Individual liner panels were joined by fusion welding and each fusion seam was subsequently non-destructively tested by air pressure.

To prevent the build up of water at the cover soil / liner interface, a geocomposite drainage material was installed over the liner providing a preferential water flow path to collection drains at the tunnel base.



Matiere Pre-cast Arch Installed


Waterproofing HDPE Liner Installed

 

General
F.L.I. Environmental has experience in both exterior and interior tunnel lining and is well placed to provide advice in the selection and technical installation of suitable geosynthetic products for these applications.

Project
Drogheda Bypass, Dublin

Main Contractor
Siac O'Rourke (JV), (ABM Construction - Tunnel Contractor)

Consultants
Roughan O'Donovan